Latest issueThree developers pitch plans for Spaeth RanchRead now

← Gillette news

County CommissionSaturday, November 7

Three developers pitched commissioners on plans for Spaeth Ranch

The Good Day Gillette teamFrom today’s edition · 1 min read · 2 sources

ShareEmailFacebookX

If you live near , here's what's on the table for the county-owned . Commissioners heard three proposals Wednesday for the more than 5,200-acre property, from CSW Development LLC and JLL, Peabody and Range Sustained Ranch.

Peabody wants to build a power plant and two data centers on the ranch, Cowboy State Daily reports. Kat Halverson, a 48-year Gillette resident who lives close by, went to the meeting expecting to oppose data centers nearby. She left saying, "They are a good company and they have a good plan for that area."

Each developer brought a different plan for the ranch

DeveloperPlan
CSW Development LLC and JLLEnergy and technology campus with a data center
PeabodyEnergy and technology park with two data centers
Range Sustained RanchWorking cattle ranch, smaller technology projects
  • Peabody's offer: $13 million for 5,289 acres
  • Peabody's park: more than $2.5 billion in capital investment
  • CSW's estimate: $2.8 billion to $4.5 billion for 300 megawatts
  • CSW's jobs: 800–1,500 in construction, 100–235 permanent

Powder River Energy Corp. told commissioners the proposed 300-megawatt development would double its current delivery load, and it would need several months of engineering studies. Fox Park residents and rural landowners raised concerns about noise and heat. CSW said it would follow a 55-decibel noise limit.

The Spaeth Ranch project would double what PRECorp delivers now

Source: County 17

View as table
Value
Current delivery load300 MW
Record peak demand450 MW
Proposed Spaeth Ranch project300 MW

Sources: County 17, Cowboy State Daily

Read it in the full edition

All city hall news
  1. County 1720 hours ago

    Three developers present proposals for Campbell County's Spaeth Ranch, on County 17

    GILLETTE, Wyo. — Campbell County commissioners heard three proposals for the county-owned Spaeth Ranch during their meeting Wednesday morning, with each developer offering a different plan for the more than 5,200-acre property. The proposals came from CSW Development LLC and JLL; Peabody; and Range Sustained Ranch. Their plans included a large data center, an energy […]

    Also reported byCowboy State Daily

  2. County 1722 hours ago

    Campbell County commissioners approve BWXT land sale notice, veterans proclamation, on County 17

    GILLETTE, Wyo. — The Campbell County Board of Commissioners approved several requests during its Nov. 4 meeting, including money for fentanyl decontamination equipment, a proclamation recognizing local veterans and agreements for county road projects. The meeting also included discussion of a proposed land sale to BWXT for a nuclear fuel facility at Pronghorn Industrial Park,

  3. Gillette News RecordNov. 5

    Data center would provide nearly $70 million to Uinta County under agreement, on Gillette News Record

    EVANSTON — A $68.3 million community endowment proposal from Prometheus Hyperscale for Evanston and Uinta County was announced Tuesday during the Uinta County Commission’s meeting.